|  12th October 2011 Before construction  20th october 2011 Excavating down 40cm  23rd october 2011 Compacted backfill with lime soil stabilizer  24th october 2011 Compacted backfill with lime soil stabilizer  25th october 2011 Preparation and laying of tar and chip surface  26th october 2011 Driving in of piled foundations  6th november 2011 Driving in of piled foundations  9th november 2011 Trimming of piles (prior to pouring the concrete foundation for the hutch)  13th november 2011 Laying of a gravel bed | |  24th october 2011 Compacted backfill with lime soil stabilizer  25th october 2011 Preparation and laying of tar and chip surface  26th october 2011 Driving in of piled foundations  27th october 2011 Driving in of piled foundations | |  26th october 2011 Driving in of piled foundations  26th october 2011 Driving in of piled foundations  27th october 2011 Driving in of piled foundations  27th october 2011 Driving in of piled foundations  27th october 2011 Driving in of piled foundations |